Veolia Central Water Treatment Plant BC Scaffold

Scaffolding services, Veolia Water Treatment BC Scaffold

Kitja Services experience with SHELL facilities and systems resulted in Veolia Australia engaging Kitja to execute the erection of and eventual dismantlement of scaffold to support their Brine Concentrator annual inspections. 

Utilizing tube and coupler systems, Kitja coordinated the engineered design and subsequent erection of scaffold to support multiple end-user contractors. 

Key activities included: 

  • Design and engineer cantilever scaffold to support upper and lower vent isolation and access
  • Coordinate material delivery and pack according to limited platform footprint
  • Liaise with Veolia operations lead to execute dismantle and erection of adjacent modules, considering crane lift timing and site SIMOPS
  • Dismantle and demobilize equipment inline with project’s critical path.

Kitja services project start icon

Commenced Feb 2022

Duration: 8 weeks

Kitja services peak resources icon

Peak Resources: 4