Millmerran Power Station Outage, 2022
Due to our team’s extensive knowledge and experience with the abrasive blasting requirements of intricate turbine components, Intergen awarded Kitja Services with a multi-year shutdown contract to execute the abrasive blasting requirements of GE HP & LP turbine components.
Kitja’s team worked closely with the General Electric project team to ensure swift turnaround of turbine components to minimize shutdown delays.
Key activities included:
- Mobilization of specialist equipment to support aluminium oxide blasting
- Quality assurance and control of all components received and returned
- Close integration with GE project critical path activities
- Managing manning level fluctuations according to deadlines and extreme weather events
Commenced April 2022
Duration: 3 weeks
Peak Resources: 6